top of page

Carriage Place Schedule
 

**This schedule may change due to inclement weather, change orders, and unforeseen conditions.
**General notices describing the full project, along with the enclosed schedule, will be posted throughout the community.
**All construction units will have a 48-hour notice posted prior to the start of work.
**All paint units will have a one-week power washing notice posted prior to the start of work.

Carriage Place Map - Landscape 20140714 (1).jpg

Loading schedule...

Carriage Place Painting Schedule

Updated at: 10/9/2026, 4:31:17 PM

Building
Address
Date
Duration
BUILDING 1
2602 - 2604
10/13/2026-10/16/2026
3
BUILDING 2
2612 - 2616
10/16/2026-10/23/2026
5
BUILDING 3
2634 - 2638
10/23/2026-10/30/2026
5
BUILDING 4
2622 - 2626
10/30/2026-11/6/2026
5
BUILDING 5
2628 - 2632
11/6/2026-11/13/2026
5
BUILDING 6
2606 - 2610
11/13/2026-11/20/2026
5
BUILDING 9
2595 - 2597
11/20/2026-11/25/2026
3
BUILDING 11
2605 - 2607
11/25/2026-11/30/2026
3

Carriage Place Construction Schedule

Updated at: 10/9/2026, 4:31:17 PM

Building
Address
Date
Duration
BUILDING 1
2602 - 2604
9/15/2026-9/22/2026
5
BUILDING 2
2612 - 2616
9/22/2026-9/24/2026
2
BUILDING 3
2634 - 2638
9/24/2026-9/29/2026
3
BUILDING 4
2622 - 2626
9/29/2026-10/2/2026
3
BUILDING 5
2628 - 2632
10/2/2026-10/7/2026
3
BUILDING 6
2606 - 2610
10/7/2026-10/13/2026
4
BUILDING 9
2595 - 2597
10/13/2026-10/19/2026
4
BUILDING 11
2605 - 2607
10/19/2026-10/22/2026
3

Schedule a free estimate.

(925) 429-2669 

4070 Nelson Ave, Suite K Concord, CA 94520

  • Google Places
  • Facebook
  • Instagram
  • YouTube

©2026 by Whit's Painting & Construction

bottom of page